Warehouse Construction Permit — Lahore

at e-Khidmat Markaz

Ask about this service
Fee
Rs. 55% of Building Plan fee for documents scrutiny to be submitted in BOP at the time of submission of documents. Building Plan Fee of Rs.5 per sq. ft. of covered area will be paid once case is approved by Chief Officer. (Fee will be calculated on total covered area in Square Feet).
Delivery time
Your sanction letter will be delivered within 21 working days.
Issued by
This service will be issued by your Relevant Municipal Corporation Lahore.
Payment
Fee payment mode will be through Bank. Bank of Punjab (Adjacent to e-Khidmat Markaz Jinnah Hall Lahore). 5 -->

The fee is not the whole cost. Undertaking of damages (BB-5) (e-Stamp Paper Rs. 1200), Bank Challan Form (Amount calculated on covered area per sq. ft.) carry their own cost on top.

Documents to take (9)

  1. Application Form (BB-1/BB-2, BB-3,BB-4)
  2. CNIC
  3. Power of Attorney/authority letter(if applicable)
  4. Registry from Sub Registrar
  5. Fresh Fard-e-Malkiat
  6. Undertaking of damages (BB-5)Cost: e-Stamp Paper Rs. 1200
  7. Structure Stability Certificate
  8. 5 Copies of Construction Plan+1 A4 copy
  9. Bank Challan FormCost: Amount calculated on covered area per sq. ft.